Location :

Darwin, NT

Client :

Sport, Recreation and Strategic Infrastructure, Department of Territory Families, Housing and Communities

Year :

2022

Sector :

Athletics | Athletics track

SPORTENG were engaged in providing a condition assessment and detailed design and documentation for the resurfacing of the Arafura Stadium Athletics Track.

This $2.6 million project was to replace the original track, which was built in 2011. The project was completed in October 2022

THE CHALLENGE

The condition of the track surface had deteriorated significantly over time and was no longer fit for state or international competition.

The old track was a full polyurethane surface, and the SPORTENG team suspected that water had been trapped under the surface and was adding to the rate of deterioration.

The track had become soft and spongy in areas, and the trapped water had turned to vapour and resulted in surface bubbling.

ArafuraAthleticTracks_OldTrack
Old track at the Arafura Stadium - Credit Polytan
old outdoor red athletic track and jumping pit being ripped up
Old athletic track being ripped up at the Arafura Stadium - Credit Polytan
old outdoor red athletic track being ripped up with machines in the background
Old athletic track being ripped up at the Arafura Stadium - Credit Polytan

THE SOLUTION

SPORTENG provided advice for remediation works to resurface the athletics track, using a red Polytan synthetic surface with specific functional requirements suited to Athletics.

The surface was poured in-situ and provides excellent sports properties such as maximum acceleration and optimum shock absorption. SPORTENG’s understanding of how climatic conditions can accelerate the degradation meant that the track system needed to be designed to account for high humidity and intense rainfall, with a more porous-based system specified to add longevity to the surface.

To further slow degradation, SPORTENG designed a composite system base layer to allow greater air and moisture movement to minimize future surface bubbling.

In addition to this, SPORTENG recommended adding additional weep holes in the drainage trench to further aid in removing moisture from the surface and suggested adjustments to the infield irrigation system to minimize overspray.

Aerial view of the asphalt layer being laid off an outdoor athletic track
New asphalt layer is being laid off at the Arafura Stadium - Credit Polytan
Men surfacing outdoor athletic track with red product
Surfacing job is being done on the new athletic track at the Arafura Stadium - Credit Polytan

THE RESULTS

The upgrade of the Arafura Stadium Athletics Track returned the facility to national athletics competition standards provided a valuable resource to the Darwin community.

Kate Worden, Minister for Sport, commented on the completion of the project “We want to see our sport start shine, that’s why Territory Labor is providing the best possible facilities for our current and further champions to use.”

Aerial view of a new outdoor red athletic track
Drone view of the new athletic track completed at the Arafura Stadium - Credit Polytan
ArafuraAthleticTracks_NewTrack